Nisga'a Highway - Culvert Installation near Ksi Gwinhak Bridge
Due to flooding near the Ksi Gwinhak Bridge area on the Nisga'a Highway, culverts will be installed.
The tentative schedule is: (Weather/Water Level dependent)
Oct. 16 Tuesday: Mobilize equipment/materials to site. Cut asphalt.
Oct. 17 Wednesday: Start Culvert installation.
Oct. 18 Thursday: Culvert Installation
Oct. 19 Friday: Complete Culvert Installation.
To be determined: Paving culvert locations.
Impact to Traffic: Single lane alternating traffic with up to 20 minute delays.
*** Please check www.drivebc.ca for up to date information regarding road work/delays.
The Ministry has commissioned a study of the creek and area to determine a long term strategy to alleviate flooding of the highway.